10.7 Temperature Measuring and Sampling Device
Ⅰ Dominant Items
10.7.1 The hydrostatic test and flushing test of water-cooled parts of temperature measuring and sampling device shall meet the requirement of the design technical document.
Quantity to be checked:100%.
Inspection method:Observe,and check the record of pressure test.
Ⅱ General Items
10.7.2 The allowable deviation for installation of temperature measuring and sampling device shall comply with the requirements in Table 10.7.2.
Quantity to be checked:100%.
Inspection method:See Table 10.7.2.
Table 10.7.2 Allowable deviation for installation of temperature measuring and sampling device